华星东方承建的河北省石家庄市晋州市生活垃圾焚烧发电提升技改项目烟气净化工程于2025年08月05号开工建设,于08月27号已安装完成通过初步验收。
The FGC system undertaken by HEPT of the waste incineration power generation upgrading project in Jinzhou, Shijiazhuang, Hebei Province, has started construction since 5th. Aug 2025 and has been finished on 27th. Aug to pass the preliminary acceptance.
该项目建设总规模1000t/d,分两期实施。一期建设规模 1×600t/d 机械炉排焚烧炉及余热锅炉+1×12MW 抽凝式汽轮发电机组,二期建设目前预留场地。烟气净化采用“SNCR脱硝+PNCR 脱硝+SDA脱酸+干法脱酸(熟石灰)+活性炭喷射吸附+袋式除尘器+ GGH+SGH+SCR脱硝+飞灰输送、存储及稳定化”的处理工艺。提升技改内容包括“SDA+袋式除尘器+飞灰输送+飞灰再熬合+渗滤液回喷+浆液输送”,为我司EPC工程。此次技改要求在28天极限工期内完成核心设备更新,是继四川宜宾项目竣工仅两个月后华星东方迎来的又一重大挑战,并再次改写了行业提标技改的完工纪录!
The total capa of this project is 1,000 tons per day and it will be implemented in two phases. The first-phase includes a 1×600t/d mechanical grate incinerator and waste heat boiler, as well as a 1×12MW extraction condensing steam turbine generator set. Currently, reserved space is available for the second-phase construction. The FGC system adopts the treatment process of "SNCR denitrification +PNCR denitrification +SDA denitrification + dry denitrification (slaked lime) + activated carbon injection adsorption + bag filter + GGH+SGH+SCR denitrification + fly ash transportation, storage and stabilization". The upgrading includes "SDA+ bag filter + fly ash conveying + fly ash re-Chelating + leachate re-injection + slurry conveying", which is an EPC project of HEPT. This technological transformation requires the completion of core equipment updates within a 28-day deadline. It is another major challenge for HEPT just two months after the completion of the project in Yibin, Sichuan. Once again it sets a new record for the completion during of technical upgrading in this industry!
在这场看似不可能完成的挑战背后,是华星东方无数的心血与汗水,以及无锡制造中心、宣城制造中心两个新投建工厂提供强大的后方支持。为了确保项目能够顺利推进,各制造中心全体员工全力保障、加班加点。从设备的整体加工制造,到精细打磨,再到最后的喷漆工序,每一个环节都严格把关,不容有失。他们深知,自己手中的每一个零件、每一台设备,都关乎着前方工程的速度与质量。
Behind this seemingly unbelievable challenge lies the countless efforts and hard work of HEPT as well as the strong support provided by the two newly built plants, which are the Wuxi Manufacturing Center and the Xuancheng Manufacturing Center. To ensure the smooth progress of the progress, all staff of each manufacturing center have been fully committed to providing efforts and working overtime. From the overall processing and manufacturing of the equipment, to the fine grinding and then to the final painting process, every process has been strictly controlled and no defects are allowed. They are well aware that every component is related to the progress and quality of the project.
值得一提的是,华星东方凭借在装备制造业领域50余年深耕制造的专业积累,实现了设备现场大模块吊装这一巨大优势。在传统模式下,设备可能需要分多次拼接以及现场制作焊接,不仅耗时费力,还容易因现场缺乏先进的加工设备及质检保障等手段造成误差而影响设备性能和工期。而此次华星东方两大制造中心将设备在工厂内完成大模块预制及拼装检验,确保万无一失后直接运输到现场进行吊装,大大缩短了施工周期,提高了施工效率,同时也保证了设备的整体性能和稳定性,使得华星东方得以在极限工期的重重压力下,有条不紊地推进各项工作,最终顺利完成既定任务,为项目的成功交付奠定了坚实基础。
Another thing worth mentioning is that, with over 50 years of professional accumulation in the equipment manufacturing industry, HEPT has achieved a significant advantage in the on-site hoisting of large modules of equipment. Under the traditional mode, equipment may need to be spliced multiple times and fabricated and welded on site. This not only takes a lot of time and effort but also is prone to defects due to the lack of advanced processing equipment and quality inspection guarantees on site, which can affect the performance of the equipment and the construction period. This time, the two manufacturing centers of HEPT have completed the large module prefabrication and assembly inspection of the equipment in the plants. After ensuring everything was qualified, they directly transported it to the site for hoisting. This significantly shortened the construction period, improved the construction efficiency and also guaranteed the overall performance and stability of the equipment. As a result, HEPT has been able to steadily advance all its work under the huge pressure of the extremely short period of construction . Ultimately, the jobs were successfully completed, laying a solid foundation for the successful delivery of the project.
面对设备交叉作业、现场施工条件严苛等重重困难,华星东方采用了“两班倒 + 模块化施工+工厂预制保障”的模式,开展 24 小时连续作业。同时,团队还充分利用 BIM 技术优化布局,通过精确的模拟和分析,提前发现并解决了潜在的设计细节错误,节省了宝贵时间。正是这种不断探索、不懈努力的精神,让华星团队在原定工期内圆满完成任务,以令人惊叹的“华星速度”刷新了环保行业技改纪录。
Facing numerous difficulties such as cross-operation of equipment and strict on-site construction conditions, HEPT staff have adopted an innovative model of "two-shift system + modular construction + factory prefabrication guarantee" to carry out 24-hour continuous operation. Meanwhile, the team also fully utilized BIM technology to optimize the layout. Through precise simulation and analysis, they have identified and resolved potential design defects in advance, saving precious time. It is precisely this spirit of continuous exploration and unremitting efforts that enabled the HEPT team to successfully complete the task within the originally scheduled schedule, setting a new record for technological transformation in the environmental protection industry with the astonishing "HEPT Speed".
华星东方在河北省的业绩涵盖包括:保定一期、二期、衡水、衡水安平、定州、沧州一期、石家庄、石家庄厦能炘、石家庄行唐、唐山曹妃甸、唐山滦州、唐山丰润、唐山洁城、唐山迁安、承德围场、保定顺平、唐山一期、二期、承德张家口北、廊坊固安、廊坊香河、廊坊三河、邢台沙河、邢台威县、邢台巨鹿、邯郸魏县等多个项目。
The references of HEPT in Hebei Province include: Baoding Phase I, Phase II, Hengshui, Hengshui Anping, Dingzhou, Cangzhou Phase I, Shijiazhuang, Shijiazhuang Xiannengxin, Shijiazhuang Xingtang, Tangshan Caofeidian, Tangshan Luanzhou, Tangshan Fengrun, Tangshan Jiecheng, Tangshan Qian 'an, Chengde Weichang, Baoding Shunping, Tangshan Phase I&II, Chengde North of Zhangjiakou, Langfang Gu 'an, Langfang Xianghe, Langfang Sanhe, Xingtai Shahe, Xingtai Wei County, Xingtai Julu, Handan Wei County, etc.