The FGC System for Wengyuan Household WtE Plant in Shaoguan, Canton, undertaken by HEPT Successfully Passes 72+24 Hour Trial Operation
2026.04.14
The FGC System for Wengyuan Household WtE Plant in Shaoguan, Canton, undertaken by HEPT, has successfully passed the 72+24 hour trial operation since 15th. April, 2025.
The total household waste treatment capacity of this project is 800 t/d and the construction will be implemented in two phases. The first phase of construction and treatment capacity is 400t/d, equipped with 1x400t/d incinerator + 1x10MW condensing turbine generator set incorporated auxiliary facilities capable of codisposals of 50t/d of kitchen waste, 20t/d of municipal sludge and 30t/d of oversized garbage. Flue gas treatment adopts the flue gas cleaning process of "SNCR denitrification in the furnace + semi-dry deacidification + dry powder spray system + activated carbon spray adsorption + bag dust collector + fly ash transportation, storage and stabilization process", all of which will be achieved by our company’s equipments.
Huaxing East's performance in Guangdong Province includes: Junye Dongguan, Nine Dragons Dongguan, Chaonan Shantou, Puning, Huiyang, Zhaoqing, Chenghai Shantou, Gaozhou, Zhongshan, Xinxing Yunfu and many other projects.